Alpine constructions at Mt Buller
2021-2022 has seen a number of developments being built. The construction season for Alpine building is only possible from October once the ski season has ended to May when the mounting prepares to commence the following ski season. Successful construction of jobs is only possible with pre planning and extreme efficiency once the jobs commence.
From October 2021 to December 2021, Chalmers Constructions completed three levels to the Kooroora West development at Mt Buller including the manufacture and installation of precast panels and floors.
January 2022 saw the completion of two floors for the penthouse extension to Buller Central at Mt Buller. Buller Central development was previously constructed by Chalmers Constructions.
February 2022 – May 2022 is a work in progress for the completion of three levels of Apartments to the Timbuktu development, Mt Buller. This was also a development previously constructed by Chalmers Constructions.